7 Commissioning of the system
7.2 Overview of the commissioning steps
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
The main commissioning steps are listed in the following table:
Step Activity Lenze software to be
used
1. Installing field devices
( 43)
2. Create a project folder
( 43)
3. Commissioning the i700 servo inverter
( 44) »PLC Designer«
Commissioning other Lenze field devices
( 70) »Engineer« /
»EASY Starter«
4. Creating a PLC program with a target system (Logic/Motion)
( 71) »PLC Designer«
5. Configuring the communication parameters
( 73)
6. Determining the physical EtherCAT configuration (fieldbus scan)
( 75)
If necessary Importing missing devices / device description files
( 78)
7. Creating a control configuration (adding field devices)
( 79)
8. Creating a task
( 82)
9. Setting a DC synchronisation
( 87)
10. Setting SoftMotion parameters
( 92)
Only required for drives with Motion functionality.
11. Processing EtherCAT I/O mapping
( 95)
Only required for drives that solely have the master functionality (logic bus).
12. Compiling the PLC program code
( 103)
13. Logging in on the controller with the »PLC Designer«
( 103)
With the log-in, the fieldbus configuration and the PLC program are loaded into
the Controller.
14. Starting the PLC program
( 103)