7 Commissioning
Initial switch−on
EDKMF2178IB DE/EN/FR 6.0
70
l
H2_FirstOn−LEDs_KommModul_BT
Initial switch−on
) Note!
Follow the commissioning steps in the given order!
1. Switch on the standard device and, if necessary, the external voltage supply of the
communication module.
The green LED 0 on the front of the communication module is lit.
The status LED of the standard device (Drive LED) 2 must be lit or blinking. The
meaning of the signalling can be found in the standard device documentation.
2. You can now communicate with the drive, i. e.
all parameters (SDO) can be read;
all writable parameters (SDO) can be overwritten.
3. After a state change ("Operational") process data can be exchanged with the drive.
2172CAN000D
Fig. 7 LEDs of the communication module