3 Commissioning
22 Lenze · Servo-Inverter 9400 HighLine · Reference manual · DMS 10.0 EN · 11/2013 · TD05/06
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
3 Commissioning
This documentation contains detailed information on parameter setting and configuration of the
controller. Sequential reading is not required.
In order to obtain the information relevant for initial commissioning, this chapter describes
different commissioning scenarios which can also be used as a guide through this manual:
A. Initial commissioning
( 25)
Target: Adapting the controller to the electromechanics and the control system.
B. Standard set-up
( 26)
Target: Taking over the application and parameter set of an already preconfigured "Engineer"
project into several controllers.
C. Controller replacement
( 27)
Target: Replacing a controller which has failed in a running system by a replacement device
using the "old" memory module.
D. Motor replacement
( 27)
Target: Replacing a motor which has failed in a running system.